3.1 Purpose and Scope
The purpose of this document is to define the acceptance test plan for the PROFINET
functionality embedded in the /91 Universal Communications Gateway module
This document focuses on the PROFINET portion of the ATP for the /91 Universal
Gateway and assumes that the BSP and EGD application code have passed the EGD
System Test Plan
The acceptance test can be broken into three distinct areas with each area focused on a
specific goal.
EGD Integration Tests
PLC Interoperability Tests
PROFINET Certification Tests
3.2 Overview
Acceptance tasks take place throughout the project life cycle and culminate in
acceptance testing.
Acceptance Testing incorporates four phases:
1. Defining the acceptance criteria
2. Developing an acceptance test plan
3. Executing the acceptance test plan
4. Reaching acceptance based on the test results
3.3 Acceptance Criteria Definition
3.3.1 Overview
This section defines the acceptance criteria and provides a high-level checklist to
enter and exit test execution.
3.3.1.1 Entrance Criteria
The entrance criteria detailed below must be completed prior to starting formal
acceptance testing:
|